CHILLICOTHE, MO — Chilli Bay, the new water park under construction at Chillicothe, is taking shape. Plumbing is completed for the 220-foot lazy river, which includes installation of an 18-inch pipe. The contractor plans to pour slabs for the lazy river during the next few weeks, weather permitting. Work on the main pool area is about complete, council members were told, with some of the pool benches now installed. The ADA ramp at the northwest corner of the area has been completed as well as the floors poured for bath houses. The contractor has told city officials that the extreme cold weather caused some plumbing delays but overall the project is considered on schedule.